Presoflex: Current activities in the Pleternica agglomeration
The implementation of the project Development of water utility infrastructure in the area of the Pleternica agglomeration, commissioned by Tekija d.o.o. Currently, the works are being performed at several locations and phases with the involvement of a larger number of people and machines.
Phase 2: Dervišaga – Kuzmica – Srednje Selo – Viškovci – Blacko
Work is underway to install a collector system in Dervišaga, Black, Kuzmica, Srednje Selo and Viškovci, where a gravity and pressure line is being installed. The construction of a pumping station, rain overflow and two retention basins is planned. 8,973 m of gravity line and 2,022 m of pressure line have been designed, and so far 916 m of pressure line and 6,311 m of gravity line have been constructed. 195 manholes and 50 house connection manholes were installed.
Phase 4: Sulkovci – Bzenica
The construction of the collector system in Bzenica and Sulkovci continued, where a gravity line with a diameter of 300 mm was installed. 6,804 m of gravity and 1,202 m of pressure line were constructed. 206 audit shafts were installed.
Phase: Frkljevci – Kadanovci:
The installation of the collector system in Frkljevci and Kadanovci is in progress, where a gravity line with a diameter of 300 mm and a pressure line are being installed. 2,216 m of gravity and 1,011 m of pressure line and 3 pumping stations have been designed. 1,706 m of gravity and 626 m of pressure line were constructed. 44 manholes and 20 manholes were installed.
Phase: Gradac
The construction of the collector system in Gradac continued, where a gravity line with a diameter of 300 mm is being installed. 5,992 m of gravity line, 284 m of pressure line and 2 pumping stations have been designed. 3,900 m of gravity and 222 m of pressure line were constructed. 119 manholes were installed
Work has also begun on the installation of shafts for house connections, and the installation of a larger number of shafts is expected in the coming period, followed by rehabilitation works on both traffic and all used and damaged areas during the works. The works are performed by the company Presoflex gradnja d.o.o. Požega.
Earthworks have started at pumping stations: CS Novoselci 1, CS Frkljevci 1, CS Pleternica 1, CS Gradac 2.
Out of the total contracted 44,595 m of the collector system on the project of the Pleternica Agglomeration, 28,150 m (63.12%) have been completed so far.